Planning Ministry contracts MTCC for three projects at three islands on November 28, 2022. (Photo/Planning Ministry)
Planning Ministry, on Monday, awarded harbor development projects at HDh. Finey and M. Muli to Maldives Transport and Contracting Company (MTCC).
The agreements pertaining to the projects were signed during a special ceremony held at Planning Ministry on Monday, with Director General Fathmath Shaana Farooq representing Planning Ministry, and CEO, Managing Director Adam Azim representing MTCC.
HDh. Finey harbor development project
The project valued at MVR 47 million will comprise of;
This project is to be completed within 450 days.
M. Muli harbor development project
The project valued at MVR 65 million will comprise of;
The project is to be completed within 550 days.
During Monday’s ceremony, MTCC was also contracted for a shore protection project at R. Rasmaadhoo for MVR 17 million.
The project which must be completed within 210 days comprises of constructing 157-meters of revetment, 45-meters of t-gryone in addition to 43-meters of gryone.
The project is to be completed within 210 days.